Client: GlaxoSmithKline S.p.A. Date: Jun 2022 – Sep 2023

OCIS has contributed to developing new hydraulic systems in the industrial utilities category to power the equipment and HVAC (facility and process) for the new premises of the production department called “FIALE 1”.

Key facts of the project

Intervention for the building P:

  • Revamping of mechanical systems for HVAC and process equipment supplies to serve the new department

Interventions for building P:

  • Technical area LYO
  • Filling area
  • Tunnel and washer area
  • Autoclaves and S.P. washer area
  • Compounding and dispensing area
  • Construction of a new refrigeration system for the production and distribution of chilled water
  • Hot water distribution from existing tie-in
  • Steam and condensate distribution from existing predisposition
  • Implementation of energy meter system
  • Installation of exhaust ventilation and drain from process equipment